    "DataSN": "9554810",
    "ArticleType": "0",
    "FileName": "",
    "Link": "",
    "Source": "https://english.dorts.gov.taipei/News_Content.aspx?n=126F1FD2E0B478E9&s=BE6CAFB0C6306A8F",
    "title": "2026 Major Administrative Plans Department of Rapid Transit Systems, Taipei City Government",
    "Content": "1.Vision&nbsp;Construct a high-quality and efficient rapid transit system that facilitates easy travel in Taipei.2.Key Results&nbsp;(1)Continually enhance the Taipei MRT network; Actively implement projects under construction; Complete construction and commence operation of the Xinyi eastern extension.&nbsp;(2) Promote urban renewal through MRT land development projects; C1/D1 construction projects to renew the Taipei West Gateway.&nbsp;3.Major Administrative Plans&nbsp;(1)Expand the network, enhance service performance, and safeguard operational safety and quality.&nbsp;A.Remove the construction fences for the Xinyi eastern extension, and the roads will be restored and returned to the public. After completion of the preliminary and final inspections, the line will commence operations. The network length will expand to 153.7 kilometers with 132 stations, enhancing the accessibility of network services.&nbsp;B.Coordinate with central government reviews for approval of comprehensive planning of the Minsheng-Xizhi line Taipei City section (11.02 kilometers with 9 stations), and simultaneously carry out basic civil works and E&M system works to shorten the overall construction schedule.&nbsp;C.Conduct a comprehensive reassessment of the Taipei MRT network, research and evaluate potential development corridors for the next 30 years, including network development in Shezi-Shilin-Beitou-Datong districts, extension of the Xinyi eastern extension to Academia Sinica, north-south corridors along Guangfu road. Continuously review and enhance the efficiency of the Taipei MRT network.&nbsp;D.Continue to conduct reviews for building permit applications, patrol work along Taipei MRT lines in compliance with the regulations of building permit bans and restrictions alongside MRT facilities, and conduct replacement tasks for the rapid transit systems in order to ensure the smooth operation of the MRT systems and the safety of MRT facilities.&nbsp;(2)Actively promote 3 Lines under construction (43.41 kilometers with 37 stations) and utilize management techniques and systems to maintain construction quality.&nbsp;A.Conduct main construction works, land acquisition and preparatory work for land development for the Circular line east section (13.25 kilometers with 10 stations).&nbsp;B.Actively accelerate projects involving civil works, as well as design review, equipment manufacturing, and testing for E&M systems for the Circular line north & south section (20.66 kilometers with 18 stations).&nbsp;C.Actively accelerate projects involving civil works, utilities and HVAC systems, as well as installation and testing of E&M systems for the Wanda line Phase I (9.5 kilometers with 9 stations).&nbsp;D.Utilize data analysis, maintain quality management systems, and administer inspections of quality planning from contractors. Promote management of material testing and verification as well as supplier quality assessments.&nbsp;(3)Continue to promote MRT land development, stimulate urban renewal, and renew the Taipei West Gateway.&nbsp;A.Conduct investor solicitation for MRT land development projects and supervise construction of the C1/D1 (Eastern Part) project.&nbsp;B.Commission contract management for the urban renewal projects of city-owned land (No.623, 3rd subsection, Muzha section).&nbsp;(4)Leverage technology services, share and transfer professional knowledge, and enhance technical capability.&nbsp;A.Continue developing, sharing and passing on the heritage of MRT-related techniques and knowledge through multiple channels.&nbsp;B.Introduce innovative technologies to enhance information services, supporting MRT construction and rental/sales services of public real estate in MRT joint-development buildings.&nbsp;C.Introduce AI technology to establish an intelligent service platform for MRT engineering knowledge, transform and preserve knowledge assets, and promote smart applications in engineering operations to enhance governmental execution efficiency.&nbsp;",
    "Files": [],
    "Links": [],
    "Pictures": [],
    "Movies": [],
    "Publish Department": "Department of Rapid Transit Systems, Taipei City Government"
  },
  {
    "DataSN": "9375795",
    "ArticleType": "0",
    "FileName": "",
    "Link": "",
    "Source": "https://english.dorts.gov.taipei/News_Content.aspx?n=126F1FD2E0B478E9&s=A53BC09FB6FD2EA9",
    "title": "2025 Major Administrative Plans Department of Rapid Transit Systems, Taipei City Government",
    "Content": "VisionConstruct a high-quality and efficient rapid transit system that facilitates easy travel in Taipei.Key ResultsContinually enhance the Taipei MRT network; Actively implement projects under construction.Promote urban renewal through Joint-Development projects; C1/D1 construction projects to renew the Taipei West Gateway.Major Administrative PlansContinue the implementation of projects involving civil works and tendering, land acquisition and preparing MRT Join-Development for the Circular line east section.Actively accelerate projects involving civil works, tracks, utilities and HVAC systems, as well as design reviews and equipment manufacturing for E&M systems. Implement land appropriation and compensation in locations related to where MRT underground tunnels pass through on the Circular line north section and south section.Actively accelerate projects involving civil works, tracks, utilities and HVAC systems, as well as construction acceptances and inspections. Implement equipment installation, integration and stability testing of E&M systems for the Xinyi eastern extension.Actively accelerate projects involving civil works, tracks, utilities and HVAC systems. Conduct design reviews, equipment manufacturing, installation and testing of E&M systems for the Wanda line Phase I.Conduct projects involving civil works, tracks, utilities and HVAC systems, as well as detail design of E&M systems. Implement land acquisition for MRT facilities for the Wanda line Phase II.Coordinate with central government reviews for approval of comprehensive planning of the Minsheng-Xizhi line Taipei City section. Review light rail transit network planning in the districts of Shezi, Shilin and Beitou in accordance with the development of Shezidao.Accelerate projects involving investor solicitation for MRT land development, supervise construction of the Taipei Main Station District Parcels C1/D1 (Eastern Part), commission urban renewal projects for two sites of city-owned land (No.623, 3rd subsection, Muzha section, etc.), and administer the sale and lease of all public real estate acquired for MRT land development.Conduct reviews for building permit applications, patrol work along Taipei MRT lines in compliance with the Regulations of Building Permit Bans and Restrictions alongside MRT Facilities, and conduct replacement tasks for Rapid Transit Systems in order to ensure the smooth operation of the MRT systems and the safety of MRT facilities.Utilize data analysis, maintain quality management systems, and administer inspections of quality planning from contractors. Promote management of material testing and verification as well as supplier quality assessments. Continue developing, sharing and passing on the heritage of MRT-related techniques and knowledge, while streamlining information services through multiple channels in order to support MRT construction, land development and service of Join-Development properties for lease and for sale.",
    "Files": [],
    "Links": [],
    "Pictures": [],
    "Movies": [],
    "Publish Department": "Department of Rapid Transit Systems, Taipei City Government"
  },
  {
    "DataSN": "9137757",
    "ArticleType": "0",
    "FileName": "",
    "Link": "",
    "Source": "https://english.dorts.gov.taipei/News_Content.aspx?n=126F1FD2E0B478E9&s=8464FC3FCB35460D",
    "title": "2024 Major Administrative Plans Department of Rapid Transit Systems, Taipei City Government ",
    "Content": "1,Vision&nbsp;Construct a high-quality and efficient rapid transit system that facilitates easy travel in Taipei.&nbsp;&nbsp;2.Key Results&nbsp;(1)Continue expanding the Taipei MRT network; &nbsp;Conduct projects under construction according to schedule and quality standards.&nbsp;(2)Promote urban renewal with the Joint-Development;&nbsp;Conduct full-scale constructions of the Taipei West Gateway C1/D1.&nbsp;&nbsp;3.Major Administrative Plans&nbsp;(1)&nbsp;Conduct projects involving civil works, tracks, utilities and HVAC systems; design reviews,equipment manufacturing and installation of E&M systems for the Wanda line Phase I.&nbsp;&nbsp;(2)Conduct projects involving civil works, tracks, utilities and HVAC systems; design reviews,equipment manufacturing and installation of E&M systems for the Xinyi eastern extension.&nbsp;&nbsp;(3)Conduct &nbsp;projects &nbsp;involving &nbsp;land &nbsp;acquisition for MRT &nbsp;facilities, &nbsp;civil &nbsp;works, &nbsp;tracks, &nbsp;utilities&nbsp;and HVAC systems; design reviews of E&M systems for the Wanda line Phase Ⅱ.&nbsp;(4)Conduct projects involving the land appropriation and compensation related to the MRTunderground tunnel passing, civil works, tracks, utilities and HVAC systems; design reviews of E&M systems for the Circular line north section and south section.&nbsp;(5)Conduct &nbsp;projects &nbsp;involving &nbsp;land &nbsp;acquisition &nbsp;for &nbsp;MRT &nbsp;facilities, &nbsp;detail &nbsp;design &nbsp;works, &nbsp;andconstruction works of the priority tender for the Circular line east section.&nbsp;&nbsp;(6)Conduct plans of the Minsheng-Xizhi line Taipei City section; review the plan of light rail transitnetwork in the districts of Shezi, Shilin, and Beitou.&nbsp;&nbsp;(7)Implement improvement projects for the elevators and escalators in the entrances/exits at thestations for the Xinlu line and Ximen Metro Mall.&nbsp;(8)Conduct investor solicitation for MRT land development projects, construction supervision forthe &nbsp;Taipei &nbsp;Main &nbsp;Station &nbsp;District &nbsp;Parcels &nbsp;C1/D1 &nbsp;(Eastern &nbsp;Part), &nbsp;commissioned &nbsp;urban renewal projects for two sites of city-owned land (No.623, 3 rd &nbsp;subsection, Muzha section, etc.) and sale and lease administrations for all the public real estate acquired from MRT land development.&nbsp;&nbsp;(9)Continue conducting reviews for building permit application, patrol work along Taipei MRT&nbsp;lines in compliance with the Regulations of Building Permit Bans and Restrictions alongside MRT Facilities, &nbsp;and replacement &nbsp;tasks &nbsp;of &nbsp;the &nbsp;Rapid Transit Systems &nbsp;in order &nbsp;to &nbsp;ensure &nbsp;a smooth operation of the MRT systems and the safety of MRT facilities.&nbsp;&nbsp;(10)Maintain quality management systems and administrate inspections on quality plans fromcontractors; &nbsp;utilize &nbsp;data &nbsp;analysis &nbsp;to &nbsp;promote &nbsp;management &nbsp;of &nbsp;material &nbsp;testing &nbsp;andverification &nbsp;as &nbsp;well &nbsp;as &nbsp;supplier &nbsp;quality &nbsp;assessments; &nbsp;continue &nbsp;developing &nbsp;and &nbsp;passing on MRT-related techniques and knowledge, and streamlining information services to support MRT construction and land development.&nbsp;",
    "Files": [],
    "Links": [],
    "Pictures": [],
    "Movies": [],
    "Publish Department": "Department of Rapid Transit Systems, Taipei City Government"
  },
  {
    "DataSN": "8908638",
    "ArticleType": "0",
    "FileName": "",
    "Link": "",
    "Source": "https://english.dorts.gov.taipei/News_Content.aspx?n=126F1FD2E0B478E9&s=44FB183323824358",
    "title": "2023 Major Administrative Plans  Department of Rapid Transit Systems, Taipei City Government",
    "Content": "1.VisionConstruct a high-quality and efficient rapid transit system that facilitates easy travel in Taipei.2.MissionConstruct a world-class rapid transit system.3.Major Administrative Plans(1) Conduct projects involving civil works, tracks, utilities and HVAC systems; design reviews of E&M systems, equipment manufacturing and installation, and premier electrical multiple units (EMUs) manufacturing for the Wanda line Phase I.(2) Conduct projects involving civil works, tracks, utilities and HVAC systems, and &nbsp;installation and tests of E&M systems for the Xinyi eastern extension.(3) Conduct projects involving land acquisition for MRT facilities, civil works, tracks, utilities and HVAC systems, and design reviews of E&M systems for the Wanda line Phase Ⅱ.(4) Conduct projects involving land acquisition for MRT facilities, civil works, tracks, utilities and HVAC systems, and design reviews of E&M systems for the Circular line north section and south section.(5) Conduct projects involving preparation of land acquisition for MRT facilities, and detail design works for the Circular line east section.(6) Review the comprehensive plans of the Minsheng-Xizhi line Taipei City section in line with the integration of the New Taipei City&rsquo;s Xizhi-Donghu line and the central government&rsquo;s Keelung MRT; review the plan of light rail transit network in the districts of Shezi, Shilin, and Beitou.(7) Implement improvement projects for the elevators and escalators in the entrances/exits at the stations for the Xinzhuang and Luzhou line.(8) Conduct investor solicitation for MRT land development projects, land development for the Taipei Main Station District Parcels C1/D1 (Eastern Part), commissioned urban renewal projects for two sites of city-owned land (No.623, 3rd subsection, Muzha section, etc.) and sale and lease administrations for all the public real estate acquired from MRT land development.(9) Continue conducting reviews for building permit application, patrol work along Taipei MRT lines in compliance with the Regulations of Building Permit Bans and Restrictions alongside MRT Facilities, and replacement tasks of the Rapid Transit Systems in order to ensure a smooth operation of the MRT systems and the safety of MRT facilities.(10) Maintain quality management systems and conduct inspections on quality plans from contractors; utilize data analysis to promote management of material testing and verification as well as supplier quality assessments; ensure implementation of the DORTS&rsquo;s strategic map into administration; continue developing and passing on MRT-related techniques and knowledge, and streamlining information services to support MRT construction and land development.",
    "Files": [],
    "Links": [],
    "Pictures": [],
    "Movies": [],
    "Publish Department": "Department of Rapid Transit Systems, Taipei City Government"
  },
  {
    "DataSN": "8539339",
    "ArticleType": "0",
    "FileName": "",
    "Link": "",
    "Source": "https://english.dorts.gov.taipei/News_Content.aspx?n=126F1FD2E0B478E9&s=D04DBE8500254606",
    "title": "2022 Major Administrative Plans Department of Rapid Transit Systems, Taipei City Government",
    "Content": "1.MissionConstruct a world-class rapid transit system.2.VisionConstruct a high-quality and efficient rapid transit system that facilitates easy travel in Taipei.3.Major Administrative Plans&nbsp;&nbsp; (1)&nbsp;Continue conducting projects involving civil works, tracks, utilities and HVAC systems, executing design reviews, equipment manufacturing and installation of E&M systems for the Wanda line Phase I.&nbsp;&nbsp; (2)&nbsp;Continue conducting projects involving civil works, tracks, utilities and HVAC systems, executing design reviews, equipment manufacturing and installation of E&M systems for the Xinyi eastern extension.&nbsp;&nbsp; (3)&nbsp;Conduct projects involving land acquisition for MRT facilities, civil works, and design reviews of E&M systems for the Wanda line Phase Ⅱ.&nbsp; &nbsp;(4)&nbsp;Conduct projects involving land acquisition for MRT facilities, civil works, and design reviews of E&M systems for the Circular line north section and south section.&nbsp;&nbsp; (5)&nbsp;Conduct projects involving comprehensive plans and environmental impact statements for central government reviews and approval, as well as the selection of detail design suppliers to initiate detail design works and the revision of urban planning for MRT facilities for the Circular line east section.&nbsp;&nbsp; (6)&nbsp;Review the comprehensive plans of the Minsheng-Xizhi line Taipei City section in line withthe integration of the New Taipei City&rsquo;s section of the Xizhi-Donghu line and the central government&rsquo;s Keelung MRT; review the plan of light rail transit network in the districts of Shezi, Shilin, and Beitou.&nbsp;&nbsp; (7)&nbsp;Implement mid-term improvement projects for the elevators and escalators in the entrances/exits at the stations that are in the confines of the initial network.&nbsp;&nbsp; (8)&nbsp;Conduct investor solicitation for MRT land development projects, land development for the Taipei Main Station District Parcels C1/D1, commissioned urban renewal projects for municipal-owned lands, and sale and lease administrations for properties obtained from MRT land development.&nbsp; &nbsp;(9)&nbsp;Continue conducting reviews for building permit application, patrol work along Taipei MRT lines in compliance with the Regulations of Building Permit Bans and Restrictions alongside MRT Facilities, and replacement tasks of the Rapid Transit Systems in order to ensure a smooth operation of the MRT systems and the safety of MRT facilities.&nbsp; &nbsp;(10) Maintain quality management systems and administrate inspections on quality plans from contractors; utilize data analysis to promote management of material testing and verification as well as supplier quality assessments; ensure implementation of the DORTS&rsquo;s strategic map into administration; continue developing and passing on MRT-related techniques and knowledge, and streamlining information services to support MRT construction and land development.",
    "Files": [],
    "Links": [],
    "Pictures": [],
    "Movies": [],
    "Publish Department": "Department of Rapid Transit Systems, Taipei City Government"
  },
  {
    "DataSN": "8369371",
    "ArticleType": "0",
    "FileName": "",
    "Link": "",
    "Source": "https://english.dorts.gov.taipei/News_Content.aspx?n=126F1FD2E0B478E9&s=70BC40C837156A88",
    "title": "2021 Major Administrative Plans Department of Rapid Transit Systems, Taipei City Government",
    "Content": "1.MissionConstruct a world-class rapid transit system.2.VisionConstruct a high-quality and efficient rapid transit system that facilitates easy travel in Taipei.3.Major Administrative Plans&nbsp;&nbsp; (1)&nbsp;Continue conducting projects involving civil works, tracks, utilities and HVAC systems, executing design reviews and equipment manufacturing of E&M systems, and MRT development area land acquisition for the Wanda line Phase I.&nbsp;&nbsp; (2)&nbsp;Continue conducting projects involving civil works, tracks, utilities and HVAC systems, executing design reviews and equipment manufacturing of E&M systems for the Xinyi eastern extension.&nbsp;&nbsp; (3)&nbsp;Conduct projects involving urban planning revisions for MRT facilities, land acquisition, civil engineering procurement, and conceptual design reviews of E&M systems for the Wanda line Phase Ⅱ.&nbsp; &nbsp;(4)&nbsp;Conduct projects involving land acquisition for MRT facilities, civil engineering procurement, and E&M systems tendering for the Circular line north section and south section.&nbsp;&nbsp; (5)&nbsp;Conduct projects involving comprehensive plans and environmental impact statements for central government reviews, as well as follow-ups on basic design, and the revision of urban planning for MRT facilities for the Circular line east section.&nbsp;&nbsp; (6)&nbsp;Review the comprehensive plans of the Minsheng-Xizhi line Taipei City section in line with the integration of the Xizhi-Donghu line and the Keelung MRT; review the plan of light rail transit network in the districts of Shezi, Shilin, and Beitou.&nbsp;&nbsp; (7)&nbsp;Implement mid-term improvement projects for the elevators and escalators in the entrances/exits at the stations that are in the confines of the initial network.&nbsp;&nbsp; (8)&nbsp;Conduct investor solicitation for MRT land development projects, land development for the Taipei Main Station District Parcels C1/D1, commissioned urban renewal projects for municipal-owned lands, and sale and lease administrations for properties obtained from MRT land development.&nbsp; &nbsp;(9)&nbsp;Continue conducting reviews for building permit application, patrol work along Taipei MRT lines in compliance with the Regulations of Building Permit Bans and Restrictions alongside MRT Facilities, and replacement tasks of the Rapid Transit Systems in order to ensure a smooth operation of the MRT systems and the safety of MRT facilities.&nbsp;&nbsp; (10)&nbsp;Maintain quality management systems and administrate inspections on quality plans from contractors; utilize data analysis to promote management of material testing and verification as well as supplier quality assessments; ensure implementation of the DORTS&rsquo;s strategic map into administration; continue developing and passing on MRT-related techniques and knowledge, and streamlining information services to support MRT construction and land development.&nbsp;",
    "Files": [],
    "Links": [],
    "Pictures": [],
    "Movies": [],
    "Publish Department": "Department of Rapid Transit Systems, Taipei City Government"
  },
  {
    "DataSN": "8157188",
    "ArticleType": "0",
    "FileName": "",
    "Link": "",
    "Source": "https://english.dorts.gov.taipei/News_Content.aspx?n=126F1FD2E0B478E9&s=2EF450BD9C235200",
    "title": "2020 Major Administrative Plans of Taipei City Department of Rapid Transit Systems",
    "Content": "1.MissionConstruct a world-class rapid transit systems.2.VisionConstruct a high-quality and efficient rapid transit systems that facilitates easy travel in Taipei.3.Major Administrative Plans&nbsp;&nbsp; (1)&nbsp;Continue conducting projects involving civil works, tracks, utilities and HVAC systems, executing design reviews of E&M systems and MRT development area land acquisition for the Wanda line Phase I and the Xinyi eastern extension.&nbsp;&nbsp; (2)&nbsp;Continue conducting projects involving the installation and testing of the equipment of E&M systems at Xinzhuang Depot on the Xinzhuang line; implementing mid-term improvement projects for the elevators and escalators in the entrances/exits of the initial network stations.&nbsp;&nbsp; (3)&nbsp;Continue implementing projects involving availability demonstration test of E&M systems, as well as acceptance of work for the Circular line Phase I.&nbsp; &nbsp;(4)&nbsp;Conducting urban planning revisions, land acquisition, and detailed design works for Wanda line Phase II and Circular line north section & south section; preparing E&M systems bidding for the Circular line north section & south section.&nbsp;&nbsp; (5)&nbsp;Conducting feasibility studies and central government reviews for approval, as well as follow-ups on comprehensive planning, the selection of technical services contractors for basic design, and the revision of urban planning for MRT facilities for the Circular line east section.&nbsp;&nbsp; (6)&nbsp;Continue implementing environmental impact statements and EPA reviews for approval, comprehensive planning for central review, and revision of urban planning for MRT facilities for the Minsheng-Xizhi line; implementing studies for the Shezi, Shilin, Beitou light rail transit network planning.&nbsp;&nbsp; (7)&nbsp;Conducting investor solicitation for MRT land development, Taipei Main Station District Parcels C1/D1 land development operations, city-owned land renewal projects (commissioned work), and property sales and rentals for municipal properties which are generated from MRT land development projects.&nbsp;&nbsp; (8)&nbsp;Continue conducting building permit application reviews and patrol operations along Taipei MRT routes in compliance with the &ldquo;Building Permit Bans and Restrictions alongside MRT Facilities&rdquo; regulations in order to ensure the safety of MRT facilities.&nbsp; &nbsp;(9)&nbsp;Continue conducting projects involving the integrated structure of MRT land development, and the installation and testing of E&M systems, as well as the preliminary and final inspections for the Taichung MRT Wuri-Wenxin-Beitun line.&nbsp;&nbsp; (10)&nbsp;Sustain quality management systems and strengthen inspections of the contractors&#39; Quality Plan; utilize data analysis to promote management performance of material testing and verification as well as supplier quality assessments; implement strategic map operations; continue establishing and passing on MRT technical expertise, and expanding information services for MRT construction and land development.&nbsp;",
    "Files": [],
    "Links": [],
    "Pictures": [],
    "Movies": [],
    "Publish Department": "Department of Rapid Transit Systems, Taipei City Government"
  },
  {
    "DataSN": "7967037",
    "ArticleType": "0",
    "FileName": "",
    "Link": "",
    "Source": "https://english.dorts.gov.taipei/News_Content.aspx?n=126F1FD2E0B478E9&s=38E2FCCA60D2AD06",
    "title": "2019 Major Administrative Plans of Taipei City Department of Rapid Transit Systems",
    "Content": "1.Mission&nbsp;&nbsp;&nbsp;Construct a world-class rapid transit systems.&nbsp;2.Vision&nbsp;&nbsp;&nbsp; Construct a high-quality and efficient rapid transit systems that facilitates easy travel in Taipei.&nbsp;3.Major Administrative Plans&nbsp;&nbsp; (1)Continue conducting projects involving civil works, tracks, utilities and HVAC systems, and&nbsp;&nbsp; &nbsp; &nbsp; &nbsp;executing design reviews of E&M systems and common ducts for the Wanda line Phase I and&nbsp; &nbsp; &nbsp; &nbsp;the Xinyi eastern extension.&nbsp;&nbsp; (2)Continue conducting projects involving civil works, tracks, utilities and HVAC systems, and&nbsp; &nbsp; &nbsp; &nbsp;executing integration and stability tests of E&M systems, as well as the preliminary and final&nbsp;&nbsp; &nbsp; &nbsp; &nbsp;inspections of the Circular line Phase I.&nbsp;&nbsp; (3)Continue conducting projects involving civil works, tracks, utilities and HVAC systems, and&nbsp; &nbsp; &nbsp; &nbsp;executing tests of as-built equipment, installation and testing of the newly purchased&nbsp; &nbsp; &nbsp; &nbsp;equipment of E&M systems at Xinzhuang Depot on the Xinzhuang line; implementing the&nbsp; &nbsp; &nbsp; &nbsp;detailed design services of the mid-term improvment project for the elevators and escalators&nbsp; &nbsp; &nbsp; &nbsp;in the entrances/exits of the initially-built network stations.&nbsp; &nbsp;(4)Continue conducting the revision of urban planning for MRT facilities, the selection of&nbsp; &nbsp; &nbsp; &nbsp;technical services contractors and detailed design for the Circular line North Section & South&nbsp; &nbsp; &nbsp; &nbsp;Section and the Wanda line Phase II.&nbsp;&nbsp; (5)Continue conducting the environmental impact statement for the Minsheng-Xizhi line as well&nbsp; &nbsp; &nbsp; &nbsp;as follow-ups of the EPA reviews and comprehensive planning; implementing feasibility&nbsp; &nbsp; &nbsp; &nbsp;studies for the Eastern Taipei North-South MRT System (the Circular line East Section) as well&nbsp; &nbsp; &nbsp; &nbsp;as follow-ups of central government reviews and comprehensive planning, and studies for&nbsp; &nbsp; &nbsp; &nbsp;the Shezi, Shilin, Beitou light rail transit network planning.&nbsp;&nbsp; (6)Continue conducting the land acquisition for the Wanda line Phase I and Xinyi eastern&nbsp; &nbsp; &nbsp; &nbsp;extension, investor solicitation for the MRT land development projects including Taipei Main&nbsp; &nbsp; &nbsp; &nbsp;Station District Parcels C1/D1, city-owned land renewal projects (commissioned work), and&nbsp; &nbsp; &nbsp; &nbsp;property sales and rentals for municipal properties that are generated from MRT join&nbsp; &nbsp; &nbsp; &nbsp;development projects.&nbsp;&nbsp; (7)Continue conducting the building permit application reviews and patrol operations along&nbsp; &nbsp; &nbsp; &nbsp;Taipei MRT routes in compliance with the regulations of&ldquo;Building Permit Bans and&nbsp; &nbsp; &nbsp; &nbsp;Restrictions alongside MRT Facilities&rdquo; in order to ensure the safety of MRT facilities.&nbsp;&nbsp; (8)Continue conducting projects involving the civil works, tracks, utilities and HVAC systems,&nbsp; &nbsp; &nbsp; &nbsp;integrated structure of MRT land development, and the availability demonstration of E&M&nbsp; &nbsp; &nbsp; &nbsp;systems for the Taichung MRT Wuri-Wenxin-Beitun line.&nbsp; &nbsp;(9)Continue conducting the commissioned work for the construction management of the&nbsp; &nbsp; &nbsp; &nbsp;installations of exterior walls and theater professional equipment for the Taipei Performing&nbsp; &nbsp; &nbsp; &nbsp;Arts Center.&nbsp;&nbsp; (10)Refine the quality management system and strengthen inspections of the contractors&#39;&nbsp; &nbsp; &nbsp; &nbsp;Quality Plan; promote management performance of material testing and verification as well&nbsp; &nbsp; &nbsp; &nbsp;as supplier quality assessments; implement the strategic map operation; continue&nbsp; &nbsp; &nbsp; &nbsp;establishing and inheriting MRT technical expertise, and expanding information services for&nbsp; &nbsp; &nbsp; &nbsp;MRT construction.",
    "Files": [],
    "Links": [],
    "Pictures": [],
    "Movies": [],
    "Publish Department": "Department of Rapid Transit Systems, Taipei City Government"
  },
  {
    "DataSN": "7636605",
    "ArticleType": "0",
    "FileName": "",
    "Link": "",
    "Source": "https://english.dorts.gov.taipei/News_Content.aspx?n=126F1FD2E0B478E9&s=CAB7539A5564E9BB",
    "title": "2018 Major Administrative Plans of Taipei City Department of Rapid Transit Systems",
    "Content": "1.Mission&nbsp;&nbsp;&nbsp;-Construct a world-class rapid transit system.&nbsp;2.Vision&nbsp;&nbsp;&nbsp; Construct a high-quality and efficient rapid transit system that facilitates easy travel in Taipei.&nbsp;3.Major Administrative Plans&nbsp;&nbsp; (1)Continue conducting projects involving civil works, tracks, utilities and HVAC systems, and&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;executing tender and design reviews of E&M systems for the Wanda-Zhonghe-Shulin line&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp; Phase I and the Xinyi eastern extension; conducting the design integration and review for&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp; the&nbsp;common duct along the Wanda-Zhonghe-Shulin line Phase I and the Xinyi eastern&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp; extension.&nbsp;&nbsp; (2)Continue implementing projects involving civil works, tracks, utilities and HVAC systems, and&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp; on-site installation and testing of E&M systems for the Circular line Phase I.&nbsp;&nbsp; (3)Continue conducting projects involving civil works, tracks, utilities and HVAC systems, and&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp; executing equipment tests and additional equipment purchases of E&M systems for&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;Xinzhuang Depot on the Xinzhuang line; conducting the selection of technical services&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp; providers entrusted and implementing the detail design services of the mid-term improving&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp; project for the elevators and escalators in the entrances of the Initially-Built Network&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp; stations; conducting the construction management of the additional MRT entrance&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp; construction for Beitou Station &nbsp;elevator installation for Zhongxiao Xinsheng Station, and&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp; escalator installation for Guting Station; conducting the construction supervision and&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp; management of all-access elevators installation for Daan and Xinyi Anhe stations on the Xinyi&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp; line.&nbsp;&nbsp; (4)Continue conducting basic design, preliminary construction surveying, and modifying of&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp; urban planning for MRT facilities on the Circular line North Section & South Section;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp; conducting basic design and modifying of urban planning for MRT facilities on the Wanda-&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp; Zhonghe-Shulin line Phase II.&nbsp;&nbsp; (5)Continue conducting comprehensive planning for the Circular line North Section & South&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp; Section, revised financial planning for the Wanda-Zhonghe-Shulin line Phase II as well as&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp; follow-ups of central government reviews, and the environmental impact assessment for the&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp; Minsheng-Xizhi line; conducting feasibility studies for the Taipei Eastern North-South rail&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;system, and studies for the Shezi, Shilin, Beitou light rail transit network planning.&nbsp;&nbsp; (6)Continue implementing land acquisition for the Wanda-Zhonghe-Shulin line Phase I and&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp; Xinyi eastern extension; investor solicitation for the MRT land development projects&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp; including Taipei Main Station District Parcel C1 and the eastern part of Parcel D1, city-owned&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp; land renewal projects (commissioned work), property sales and rentals for municipal&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp; properties that are generated from MRT Join Development projects, and monitoring of the&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp; Taipei MRT Joint Development fund execution.&nbsp;&nbsp; (7)Continue conducting the building permit application reviews and patrol operations along&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;Taipei MRT system in compliance with the regulations of &ldquo;Building Restriction along MRT&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp; Facilities&rdquo; in order to ensure the safety of MRT facilities.&nbsp;&nbsp; (8)Continue conducting projects involving the civil works, tracks, utilities and HVAC systems,&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp; integrated structure of MRT land development, and E&M systems on-site installation and&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;tests for the Taichung MRT Wuri-Wenxin-Beitun line.&nbsp;&nbsp; (9)Continue conducting the commissioned projects on the construction management of the&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp; installations of exterior walls and theater professional equipment for Taipei Performing Arts&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp; Center, Daan Elderly Service & Day Care Center, and Beitou Qiyang Elderly LOHAS Building.&nbsp;&nbsp; (10)Refine the quality management system following the organizational reform of DORTS;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;strengthen inspections of construction quality planning of the contractors; promote&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp; management performance of material testing and verification as well as supplier quality&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp; assessments; implement the strategic map operation, and strengthen efficiency management&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp; of official document processing; passing down of the legacies of MRT professional&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp; experience and expanding of the information services for MRT construction.",
    "Files": [],
    "Links": [],
    "Pictures": [],
    "Movies": [],
    "Publish Department": "Department of Rapid Transit Systems, Taipei City Government"
  },
  {
    "DataSN": "5769351",
    "ArticleType": "0",
    "FileName": "",
    "Link": "",
    "Source": "https://english.dorts.gov.taipei/News_Content.aspx?n=126F1FD2E0B478E9&s=7FBE9366F44E8EFB",
    "title": "2017 Major Administrative Plans of Taipei City Department of Rapid Transit Systems",
    "Content": "Mission- Construct a world-class rapid transit system.&nbsp;VisionConstruct a high-quality and efficient rapid transit system that facilitates easy travel in Taipei.&nbsp;Major Administrative Plans(1)Continue conducting the projects involving civil works, utilities and HVAC systems, and E&M systems tendering for the Wanda-Zhonghe-Shulin line Phase I; conducting civil works, and E&M systems tendering and design review for the Xinyi eastern extension.(2)Continue implementing the projects involving civil works, tracks, utilities and HVAC systems, and E&M systems detail design, equipment manufacturing, deliveries, on-site installation and testing for the Circular line Phase I.(3)Continue conducting the projects involving civil works, tracks, utilities and HVAC systems, exiting equipment tests and additional equipment purchases of E&M systems for Xinzhuang Depot on the Xinzhuang line; implementing management of additional MRT entrance construction and elevator installation for Jiantan Station on the Tamsui line, additional MRT entrance construction for Beitou Station, elevator installation for Zhongxiao Xinsheng Station, and escalator installation for Guting Station.(4)Continue conducting basic design and preliminary construction surveying for the Circular line North Section & South Section, and basic design for the Wanda-Zhonghe-Shulin line Phase II.(5)Continue conducting comprehensive planning for the Minsheng-Xizhi line, Circular line North Section & South Section, and revised financial planning for the Wanda-Zhonghe-Shulin line Phase II as well as follow-ups of central government reviews; feasibility studies for the Eastern Taipei North-South rail system, and Shezi, Shilin, Beitou light rail transit network.(6)Continue implementing land acquisition for the Wanda-Zhonghe-Shulin line Phase I and Xinyi eastern extension; investor solicitation for the MRT land development projects including Taipei Main Station District Parcel C1 and the eastern part of Parcel D1, and the city-owned land renewal projects (commissioned work).(7)Continue conducting the building permit application review and patrol operations along Taipei MRT system in compliance with the regulations of &ldquo;Building Restriction along MRT Facilities&rdquo; in order to ensure the safety of MRT facilities.(8)Continue conducting the projects involving the civil works, tracks, utilities and HVAC systems, and E&M systems equipment manufacturing, deliveries, on-site installation and tests for the Taichung MRT Wuri-Wenxin-Beitun line.(9)Commissioned Projects: Continue conducting the commissioned projects on the construction management of Taipei Performing Arts Center, the 2017 Taipei Universiade Stadium (including the Heping Elementary School Basketball Stadium, and Taipei City Tennis Sports Center), the Taipei Astronomical Museum exhibition hall renovation and special exhibition area expansion; Daan Elderly Service & Day Care Center, and Beitou Qiyang Elderly LOHAS Building.(10)Enhance quality management (including an internal control system) and implementation of risk management; strengthen inspections of construction management and construction quality of the contractors; promote management performance of material testing and verification as well as supplier quality assessments; implement the strategic map operation, and strengthen the document aging control; promote the transmission and learning of MRT technology, and cultivate core technology professionals..",
    "Files": [],
    "Links": [],
    "Pictures": [],
    "Movies": [],
    "Publish Department": "Department of Rapid Transit Systems, Taipei City Government"
  },
  {
    "DataSN": "3248610",
    "ArticleType": "0",
    "FileName": "",
    "Link": "",
    "Source": "https://english.dorts.gov.taipei/News_Content.aspx?n=126F1FD2E0B478E9&s=2BDC9843C7345775",
    "title": "2016 Major Administrative Plans of Taipei City Department of Rapid Transit Systems",
    "Content": "Mission- Construct a safe and high-quality rapid transit system- Pursue user-oriented and convenient system features&nbsp;VisionConstruct a high-quality and efficient rapid transit system that facilitates easy travel in Taipei.&nbsp;Major Administrative Plans(1) Continue conducting civil works tendering and construction, and E&M systems tendering preparation for the Wanda-Zhonghe-Shulin line Phase I; conducting civil works tendering and construction, and carrying out E&M systems tendering for the Xinyi eastern extension.(2) Continue conducting civil works, trackwork, utilities and HVAC systems, E&M systems equipment manufacturing, deliveries, on-site installation and tests for the Circular line Phase I.(3) Commissioned projects for Bureau of High Speed Rail, MOTC include:Implementing underground construction of the Sanchong-Taipei section and Taiwan Taoyuan International Airport MRT line, management of the hand-over issues for operation, and construction management of the underground passageway connection between Taipei(A1) station and Zhengzhou Road underground shopping mall.(4) Continue conducting civil works, track work, utilities and HVAC systems construction, and E&M systems tender invitations for Xinzhuang Depot on the Xinzhuang line; implementing additional MRT entrance construction and elevator installation for Jiantan Station on the Tamsui line, and design of additional elevators and installation management for Beitou, Zhongsiao Xinsheng stations.(5) Continue conducting basic design and preliminary survey works for the Circular line north section & south section.(6) Continue conducting comprehensive plans for the Minsheng-Xizhi line, Circular line North Section & South Section, and financial planing for the Wanda-Zhonghe-Shulin line Phase II as well as follow-ups of central government reviews; feasibility studies for the Shezi-Shilin-Beitou light rail transit network, North-South line, Sanying extension to Bade, and Taipei MRT extension to Chitu Bedford Community.(7) Continue implementing investor solicitation tendering for the MRT land development projects, city-owned land renewal projects (commissioned work); superficies registration or acquisition for the land used for stations, explanatory notes and compensation processes due to MRT under-passes, and land acquisition on the Joint Development areas through negotiation and purchase on the Wanda-Zhonghe-Shulin line Phase I and Xinyi eastern extension.(8) Taichung MRT Wuri-Wenxin-Beitun Line Construction:Continue conducting civil works and track work construction, E&M systems equipment/facilities detail design, procurement, and manufacturing and installation.(9) Commissioned Projects:Continue conducting construction management of Taipei Performing Arts Center, the 2017 Taipei Universiade Stadium (including the Heping Elementary School Basketball Stadium, and Taipei City Tennis Sports Center), the Taipei Astronomical Museum exhibition hall renovation and special exhibition area expansion; Daan Elderly Service & Day Care Center, Beitou Qiyang Elderly LOHAS Building; and MRT Joint Development Building integration with Taipei Mandarin Experimental Elementary School.　(10)Enhance quality management (including internal control) and implementation of risk management. Strengthen inspections of construction quality and construction management efficiency. Promote management performance of material testing and verification as well as supplier quality assessment. Improve training and inspection of official documents. Expand the GIS application and the cloud service for mobile devices.",
    "Files": [],
    "Links": [],
    "Pictures": [],
    "Movies": [],
    "Publish Department": "Department of Rapid Transit Systems, Taipei City Government"
  },
  {
    "DataSN": "3248612",
    "ArticleType": "0",
    "FileName": "",
    "Link": "",
    "Source": "https://english.dorts.gov.taipei/News_Content.aspx?n=126F1FD2E0B478E9&s=93BD245828F1C73F",
    "title": "2015 Major Administrative Plans of Taipei City Department of Rapid Transit Systems",
    "Content": "Mission - Construct a safe rapid transit system- Pursue user-oriented system featuresVisionConstruct a high-quality and efficient rapid transit system that facilitates easy travel in Taipei.Major Administrative Plans(1) Tucheng Extension to Dingpu Construction: Continue construction inspections, systemwide stability tests, preliminary and final inspections, and preparations for operation. (2) Complete Sanchong to Taipei City Section, Taiwan Taoyuan International Airport Line Construction: Continue conducting civil works and utilities and HVAC systems tests. (3) Continue conducting civil works, trackwork, utilities and HVAC systems, E&M systems equipment manufacturing, deliver, and installation for the Circular line Phase I. (4) Wanda-Zhonghe-Shulin Line Phase I and Xinyi Eastern Extension Construction: Continue conducting civil works tendering and construction as well as E&M systems tendering preparations and detailed design for the Wanda-Zhonghe-Shulin line Phase I. Continue conducting detailed design, civil works tendering and construction, and additional E&M systems procurement for the Xinyi eastern extension. (5) Continue conducting civil works, trackwork, utilities and HVAC systems for Xinzhuang Depot on the Xinzhuang line. (6) Continue conducting feasibility studies, comprehensive plans, financial plans, and environmental impact assessment reports for the Minsheng-Xizhi line, north and south sections of the Circular line, Shezi-Shilin-Beitou light rail transit network, North-South line, Sanying line, and Ankeng line, as well as follow-up of central government reviews. (7) Continue implementing MRT land development projects, city-owned land renewal projects, the land development project on Taipei Main Station District Parcel C1 and the eastern section of Parcel D1, the land acquisition and compensation process for Wanda-Zhonghe-Shulin Line Phase I. (8) Taichung MRT Wuri-Wenxin-Beitun Line Construction: Continue conducting civil works; E&M systems equipment/facilities procurement, manufacturing and installation tests. (9) Commissioned Projects: Continue conducting construction management of Taipei Taipei Performing Arts Center. Design and construction management for the 2017 Taipei Universiade Stadium including the Heping Elementary School Basketball Stadium, Taipei City Tennis Sports Center, and the underpass between the Taipei Dome Complex and Sun Yat-sen Memorial Hall and the south entrance. Tendering and construction management of the Taipei Astronomical Museum exhibition hall renovation and special exhibition area expansion. (10) Enhance quality management (including internal control) and implementation of risk management. Strengthen inspections of construction quality and construction management efficiency. Promote management performance of material testing and verification as well as supplier quality assessment. Improve training and inspection of official documents. Expand the application of GIS service. Promote the cloud service of the mobile devices. ",
    "Files": [],
    "Links": [],
    "Pictures": [],
    "Movies": [],
    "Publish Department": "Department of Rapid Transit Systems, Taipei City Government"
  },
  {
    "DataSN": "3248614",
    "ArticleType": "0",
    "FileName": "",
    "Link": "",
    "Source": "https://english.dorts.gov.taipei/News_Content.aspx?n=126F1FD2E0B478E9&s=D4F8DC93B55EDCF9",
    "title": "2014 Major Administrative Plans of Taipei City Department of Rapid Transit Systems",
    "Content": "Mission- Construct a safe rapid transit system- Pursue user-oriented system features- Adhere to high-quality construction&nbsp;Vision&nbsp;Construct a high-quality and efficient rapid transit system that facilitates easy travel in Taipei.&nbsp;Major Administrative Plans facilitates easy travel in Taipei.&nbsp;(1) Songshan Line Construction (Including Common Ducts):Continue conducting civil works, utilities and HVAC systems, systemwide integration tests, system stability tests, preliminary and final inspections, and preparations for operation.(2) Circular Line Phase I and Tucheng Extension to Dingpu Construction:Continue conducting civil works, trackwork, utilities and HVAC systems, E&M systems detailed design, and equipment manufacturing and installation for the Circular line Phase I. Continue conducting E&M systems static and dynamic tests for the Tucheng extension to Dingpu.(3) Wanda-Zhonghe-Shulin Line Phase I and Xinyi Eastern Extension Construction:Continue conducting civil works tendering and construction as well as E&M systems tendering preparations for the Wanda-Zhonghe-Shulin line Phase I. Continue conducting detailed design, civil works tendering and construction, and additional E&M systems procurement for the Xinyi eastern extension.(4) Continue conducting civil works, trackwork, utilities and HVAC systems for Xinzhuang Depot on the Xinzhuang line.(5) Taichung MRT Wuri-Wenxin-Beitun Line Construction:Continue conducting civil works; E&M systems detailed design, and equipment/facilities procurement and manufacturing.(6) Sanchong to Taipei City Section, Taiwan Taoyuan International Airport Line Construction:Continue conducting civil works as well as utilities and HVAC systems.(7) Commissioned Projects:Continue conducting construction management of Taipei Children&rsquo;s Amusement Park (including ride facilities) and Taipei Performing Arts Center; design and construction management of the Heping Elementary School Basketball Stadium and Taipei City Tennis Sports Center; tendering and construction management of the Taipei Astronomical Museum exhibition hall renovation and special exhibition area expansion.(8) Continue conducting feasibility studies, comprehensive plans, financial plans, and environmental impact assessment reports for the Minsheng-Xizhi line, north and south sections of the Circular line, Shezi-Shilin-Beitou light rail transit network, North-South line, Sanying line, and Ankeng line, as well as follow-up of central government reviews.(9) Continue implementing MRT land development projects, city-owned land renewal projects entrusted by Taipei City Government, investor solicitation for the land development project on Taipei Main Station District Parcel C1 and the eastern section of Parcel D1, and investor selection for the Circular line Phase I land development project.(10) Enhance quality management (including internal control) and implementation of risk management. Strengthen inspections of construction quality and construction management efficiency. Promote management performance of material testing and verification as well as supplier quality assessment. Improve training and inspection of official documents. Promote wide application of electronic and mobile devices. Expedite application of construction management electronic signatures.",
    "Files": [],
    "Links": [],
    "Pictures": [],
    "Movies": [],
    "Publish Department": "Department of Rapid Transit Systems, Taipei City Government"
  },
  {
    "DataSN": "3248621",
    "ArticleType": "0",
    "FileName": "",
    "Link": "",
    "Source": "https://english.dorts.gov.taipei/News_Content.aspx?n=126F1FD2E0B478E9&s=AC0A58843C5CEF80",
    "title": "2011 Major Administrative Plans of Taipei City Department of Rapid Transit Systems",
    "Content": "Mission - Perform safe rapid transit construction- Pursue a human-oriented rapid transit system- Build a rapid transit system using high quality engineering- Create a sustainable rapid transit environment- Forge a new world-class metropolisVisionConstruct a high quality and efficient rapid transit system allowing easy travel in Taipei, and build an optimal MRT network up to 270 km in length.Major Administrative Plans (1) Continue implementing construction of the Xinzhuang line:- The work scope of the section from Xinzhuang Depot to Taipei Bridge Station and the section from Dongmen Station to Guting Station of the Xinzhuang line includes civil engineering and architectural work, trackwork, installation of heat, ventilation & air-conditioning (HVAC) systems, integrated testing of the systemwide electrical and mechanical (E&M) systems, preliminary and final inspections, and preparations for inauguration.- The work scope of the Xinzhuang line New Taipei City section (Xinzhuang Depot excluded) includes processing completion & acceptance of the construction project, overseeing the manufacture, installation and testing of systemwide E&M facilities of the entire Xinzhuang line. (2) Expedite construction of the Xinyi and Songshan lines:Continue implementing civil engineering and architectural work;perform trackwork; install heat, ventilation & air-conditioning (HVAC) systems; perform integrated testing of the systemwide electrical and mechanical (E&M) systems; construct common utility ducts; conduct design; oversee manufacture of the systemwide E&M facilities as well as the manufacture and assemblage of the electric multiple units (EMUs). (3) Expedite construction of the Circular line Phase I and the Tucheng extension to Dingpu. The work scope includes civil engineering and architectural work, systemwide E&M facilities, and detailed design of the electric multiple units (EMUs).(4) Expedite construction of the Taichung Metropolitan MRT Wuri-Wenxin-Beitun line, including tendering and construction of the civil engineering and architectural work, as well as tendering and detailed design of the systemwide E&M facilities and electric multiple units (EMUs).(5) Expedite construction of the Taiwan Taoyuan International Airport Access MRT System's Sanchong-Taipei section. The work scope includes implementation of the civil engineering work.(6) Continue construction of the Taipei Children’s Amusement Park, perform exhibition maintenance of the Yuanshan Exhibition Venue of the 2010 Taipei International Flora Expo, and process completion & acceptance of the construction project.(7) Conduct detailed design of the civil engineering and architectural work, urban rezoning, and land acquisition for the Xinyi eastern extension and the Wanda line Phase I.(8) Continue feasibility studies, drawing up of planning reports, financial plan reports, and environmental impact assessment reports for the North-South line, Minsheng-Xizhi line, Ankeng line, Sanying line, Shezi, Shilin, Beitou light rail lines, and the north and south sections of the Circular line in accordance with central government’s reviews.(9) Continue implementing work items as follows: MRT land development projects, site selection, negotiating and contracting with landowners, architectural concept design, investor selection, rights and interests allocation, contract implementation, real estate management, fund management, and drawing up of related laws and regulations for land development; city-owned land development projects and urban renewal commissioned by other related departments; Taipei Main Station District Parcel C1 and the eastern part of Parcel D1 joint development project; land acquisition through negotiation and purchase as well as drawing up of investor selection documents for the Circular line; budget preparation for construction of the Taiwan Taoyuan International Airport Access MRT System and the Circular line Phase I; provide technical consulting services to the “Taichung Metropolitan MRT Wuri-Wenxin-Beitun Line Depot & Station Land Development Project.”(10) Gradually improve the transmission speed of the wide area network (WAN) used by DORTS’ district project offices to promote integrated information system efficiency; introduce the Building Information Model (BIM) to increase the efficiency of construction management; expand the overall indexing platform to upgrade automatic sorting functionality and increase search speed and accuracy; continue to promote knowledge management to be applied to MRT consulting services, MRT technical training, and the compilation of MRT Technology Book Series.",
    "Files": [],
    "Links": [],
    "Pictures": [],
    "Movies": [],
    "Publish Department": "Department of Rapid Transit Systems, Taipei City Government"
  },
  {
    "DataSN": "3248619",
    "ArticleType": "0",
    "FileName": "",
    "Link": "",
    "Source": "https://english.dorts.gov.taipei/News_Content.aspx?n=126F1FD2E0B478E9&s=A8700162305B07A8",
    "title": "2010 Major Administrative Plans of Taipei City Department of Rapid Transit Systems",
    "Content": "Complete construction of the section from the Luzhou line’s Luzhou Station to the Xinzhuang line’s Zhongxiao Xinsheng Station and the section from Nangang Station to Taipei Nangang Exhibition Center Station on the Nangang eastern extension:Complete civil engineering and architectural work, facility manufacture, installation and testing of the systemwide electrical and mechanical (E&M) systems, system-integration tests, initial and final system inspections, and preparations for inauguration.Continue construction of the section from Xinzhuang Depot to Taipei Bridge Station and the section from Dongmen Station to Guting Station on the Xinzhuang line:Construct civil engineering work, trackwork, install heat, ventilation & air-conditioning (HVAC) systems and oversee the manufacture and installation and tests of systemwide E&M facilities.Expedite construction of the Xinyi and Songshan lines:Continue implementing civil engineering and architectural work, trackwork, common utility duct construction and installation of heat, ventilation & air-conditioning (HVAC) systems.Oversee the manufacture, installation and testing of systemwide E&M facilities and assemblage of electric multiple units (EMUs).Expedite construction of the Sanchong-Taipei section of the Taiwan Taoyuan International Airport Access MRT System:Continue implementing civil engineering and architectural work.Expedite construction of the Circular line Phase I and the Tucheng extension to Dingpu:Conduct land acquisition, tendering for civil engineering and architectural work; and construction of the Circular line Phase I; implement civil engineering and architectural work of the Tucheng extension to Dingpu, the detailed design of the systemwide E&M system and EMUs of the Circular line Phase I, as well as the Tucheng extension to Dingpu.Complete construction of the Yuanshan Exhibition Venue of the 2010 Taipei International Flora Expo tendering and construction of the Taipei Children’s Amusement Park; conduct the construction contract management of the Taipei City Hakka Culture Theme Park & Cross-Embankment Platform Square.Expedite construction of the Taichung Metropolitan MRT Wuri-Wenxin-Beitun line:Implement tendering and construction of civil engineering and architectural work; conduct tendering and detailed design of systemwide E&M work and EMUs.Prepare a budget and have it approved for the Xinyi eastern extension and the Wanda line Phase I; conduct detailed design of the civil engineering and architectural work; implement urban rezoning and land acquisition.Continue the drawing up of planning reports, financial plan reports, and environmental impact assessment reports for the North-South line, Minsheng-Xizhi line, Ankeng line, Sanying line, Shezi, Shilin, Beitou Light Rail lines, plus north and south sections of the Circular line in accordance with the central government’s reviews.Continue implementing MRT land development projects, site selection, negotiating and contracting with landowners, architectural concept design, investor selection, rights and interests allocation, contract implementation, real estate management, fund management, and the drawing up of related  regulations for city-owned land development, and urban renewal commissioned by Taipei City government’s related departments, land acquisition through negotiation and purchase for the Circular line, the drawing up of investor selection documents; conduct budget preparation for  construction of the Taiwan Taoyuan International Airport Access MRT System and the Circular line Phase I; Provide technical consultation services to the “Taichung Metropolitan MRT Wuri-Wenxin-Beitun line Depot & Station Land Development Project,” and the “Taoyuan Metropolitan MRT Network Planning and Land Development Project.”Improve overall information technology system performance; test application systems for date-related bugs; establish a Web2.0 IT operation environment, conduct professional MRT technology training; continue promoting  knowledge management to applying it in MRT consulting services and  Technology Book Series.Enhance fulfillment of quality management (internal control systems) and improve inspection of contractors’ major construction items and fulfillment levels of construction quality plans; increase management effectiveness of material tests and material verification; strengthen training, checking and approval of official documentation; improve official documentation quality and maintain zero-delay performance in dealing with official documentation; reflect current construction status and increase management effectiveness of each project under the supervision of the Taipei City Council and Taipei City government, so as to strengthen the harmonious relationship between DORTS and city councilors.",
    "Files": [],
    "Links": [],
    "Pictures": [],
    "Movies": [],
    "Publish Department": "Department of Rapid Transit Systems, Taipei City Government"
  },
  {
    "DataSN": "3248617",
    "ArticleType": "0",
    "FileName": "",
    "Link": "",
    "Source": "https://english.dorts.gov.taipei/News_Content.aspx?n=126F1FD2E0B478E9&s=AB70E348A692765D",
    "title": "2009 Major Administrative Plans of Taipei City Department of Rapid Transit Systems",
    "Content": "1. Complete construction of the Neihu line:Complete civil engineering work, manufacture and installation of systemwide electrical and mechanical (E&M) facilities, system-integration tests, initial and final system inspections, and preparations for inauguration.2. Expedite construction of the Xinzhuang and Luzhou lines, and the Nangang eastern extension:Continue implementing civil engineering, trackwork, and the heat, ventilation & air-conditioning (HVAC) systems; oversee the manufacture and installation of systemwide E&M facilities and conduct related tests; continue civil engineering and systemwide E&M engineering work for the Nangang eastern extension from Nangang Station to Taipei Nangang Exhibition Center Station.3. Expedite construction of the Xinyi and Songshan lines:Continue implementing civil engineering, trackwork, and the heat, ventilation & air-conditioning (HVAC) systems, as well as common utility duct construction; implement systemwide E&M work and detailed design of electric multiple units (EMUs).4. Expedite construction of the Taiwan Taoyuan International Airport Access MRT System&#39;s Sanchong-Taipei section:Continue implementing civil engineering work; complete the detailed design of the joint development (JD) building on Parcel C1.5. Expedite construction of the Circular line Phase I and the Tucheng extension to Dingpu:Conduct civil engineering detailed design, land acquisition, tendering, and civil engineering work; implement the detailed design of the systemwide E&M system and EMUs of the Circular line Phase I, as well as the Tucheng extension to Dingpu systemwide E&M system detailed design.6. Expedite construction of Yuanshan Exhibition Venue of the 2010 Taipei International Flora Expo and conduct contract management of the Taipei Bus Station BOT project on Parcel No. T9.7. Continue the drawing up of planning reports, financial plan reports, and environmental impact assessment reports for the Ankeng line, Sanying line, Xinyi eastern extension, Shezi, Shilin, Beitou light rail lines, Wanda-Zhonghe-Shulin line, North-South line, and Minsheng-Xizhi line in accordance with central government reviews.8. Continue implementing MRT land development projects, site selection, negotiating and contracting with landowners, architectural concept design, investor selection, rights and interests allocation, contract implementation, real estate management, fund management, and the drawing up of related laws and regulations for land development, city-owned land development projects and urban renewal commissioned by other related departments, land acquisition through negotiation and purchase for the Circular line, the drawing up of investor selection documents; provide technical consultation services to the &quot;Taichung Metropolitan MRT Wuri-Wenxin-Beitun Line Depot & Station Land Development Project,&quot; and the &quot;Taoyuan Metropolitan MRT Network Planning and Land Development Project.&quot;9. Improve overall information technology (IT) system performance; update UNIX computer system; update DORTS&#39; whole IT network framework; initiate the government service network (GSN) to connect district project offices and site offices with DORTS&#39; Intranet; continue promoting knowledge management to shape an organizational culture of learning; establish Web2.0 IT operation environment.10. Enhance fulfillment of quality control (internal systems) and strengthen inspection of contractors&#39; major construction items and fulfillment of quality plans; enhance management efficiency of material tests and material verification; strengthen the training, checking and approval of official documentation; improve official documentation quality and maintain zero-delay performance in dealing with official documentation; reflect current construction status and increase management efficiency of each project under the supervision of the Executive Yuan and Taipei City government.",
    "Files": [],
    "Links": [],
    "Pictures": [],
    "Movies": [],
    "Publish Department": "Department of Rapid Transit Systems, Taipei City Government"
  }
]